20 tons
Approximately 44,000 lb holding capacity.
Plant 1 is being prepared around a 20-ton reverberatory furnace and an initial alloy program focused on 356 and 1xxx-series aluminum.


Phase 1
Approximately 44,000 lb holding capacity.
Approximately 88,000–110,000 lb/day.
Approximately 2.2 million lb/month.
Current one-furnace planning range.
Planned alloy program
Principal raw-material stream: aluminum wheels.
Raw material: suitable local and production scrap.
The final product mix will depend on customer requirements, raw-material availability, equipment configuration, and production requirements.
Launch roadmap
A simple milestone view of the preparation program. The primary target is the first ingot cast in March 2027.
~50,000 sq ft prepared, with an additional ~66,000 sq ft planned to come into service.
Phase 1 furnace in production.
Environmental approvals and final operational preparations ahead of production startup.
Primary launch milestone for Plant 1.
Quality management system and environmental compliance certification.